Home › New York › Livingston County › November 2026
Livingston County power outages in November 2026
5 unplanned outages so far this month (through November 24), reaching 511 customers in all; the typical one lasted 1 hr 31 min.
- Unplanned outages
- 5plus 0 planned
- Customers affected
- 511each outage counted at its peak
- Typical length
- 1 hr 31 minmedian of 5 ended outages
- Most out at once
- 505Nov 24, 2026, 2:10 PM EST
Outages per day
Largest outages
- 493at peak
Back at 2:20 PM
out 1 hr 11 min - 12at peak
Back at 3:30 PM
out 1 hr 31 min - 4at peak
Back at 1:55 PM
out 34 min - 1at peak
Back at 10:20 PM
out 5 hr 49 min - 1at peak
Back at 10:20 PM
out 6 hr 46 min
Longest outages
- 12at peak
Back at 3:30 PM
out 1 hr 31 min - 493at peak
Back at 2:20 PM
out 1 hr 11 min
By utility
| Utility | Outages | Customers affected |
|---|---|---|
| National Grid | 5 | 511 |
Causes
| Cause, as the utility gave it | Outages | Share |
|---|---|---|
| Unknown | 5 | 100% |
Many outages are listed before the cause is known; utilities don't always update it.
Livingston County power outages right now
“Customers affected” adds up each outage's peak, so a home that lost power twice counts twice. Covers outages that Central Hudson, National Grid and NYSEG and RG&E report to the Outage Data Initiative Nationwide (ODIN), run by the U.S. Department of Energy and Oak Ridge National Laboratory.