Home › Kansas › Douglas County › November 2026
Douglas County power outages in November 2026
4 unplanned outages so far this month (through November 24), reaching 21 customers in all; the typical one lasted 42 min.
- Unplanned outages
- 4plus 0 planned
- Customers affected
- 21each outage counted at its peak
- Typical length
- 42 minmedian of 4 ended outages
- Most out at once
- 14Nov 24, 2026, 10:30 AM CST
Outages per day
Largest outages
- 13at peak
Back at 11:00 AM CT
out 37 min - 6at peak
Back at 8:20 PM CT
out 18 min - 1at peak
Back at 12:30 PM CT
out 46 min - 1at peak
Back at 11:40 AM CT
out 1 hr 32 min
Longest outages
- 13at peak
Back at 11:00 AM CT
out 37 min
By utility
| Utility | Outages | Customers affected |
|---|---|---|
| Evergy | 4 | 21 |
Causes
| Cause, as the utility gave it | Outages | Share |
|---|---|---|
| Cause not given yet | 4 | 100% |
Many outages are listed before the cause is known; utilities don't always update it.
Douglas County power outages right now
“Customers affected” adds up each outage's peak, so a home that lost power twice counts twice. Covers outages that Butler REC, Evergy and Victory Electric report to the Outage Data Initiative Nationwide (ODIN), run by the U.S. Department of Energy and Oak Ridge National Laboratory.