Home › California › Tulare County › This outage
Power back by 4:20 PM
2 customers at the peakout about 15 hr 19 min
Power back in Woodlake after planned SCE outage
Southern California Edison reported a planned outage in Woodlake that began 1:01 AM and reached 2 customers. Cause: planned work: equipment upgrade. It was no longer listed by 4:20 PM.
SCE's first estimate was 2:00 PM; power was back 2 hr 21 min after that.
- Utility
- Southern California Edison (SCE)
- Customers at peak
- 2
- Cause
- Planned work: equipment upgrade
- Type
- Planned (scheduled work)
- Began
- Nov 24, 2026, 1:01 AM PST
- Power back by
- Nov 24, 2026, 4:20 PM PST
- Lasted
- About 15 hr 19 min
- Where
- in Woodlake, Tulare County
- Out now
- Planned
- Power back
- Bigger circle: more customers. Points are approximate.
The point is the utility's approximate location for the outage, not each address affected. To check your address or report an outage, use SCE's outage map.
Timeline
- First listed: 2 customers out, estimated back by 2:00 PM.
- Estimate changed from 2:00 PM to 3:15 PM.
- No longer listed: power back for the planned outage.
Other outages nearby
No other outages within 10 miles right now.
More for this area
- Power outages in and near Woodlake
- Tulare County power outages
- SCE outages across California
- Crashes and road closures in Tulare County (Crash Bulletin)
Source: California outage data: California Governor's Office of Emergency Services (Cal OES), Power Outage Incidents layer, compiled from the utilities' public outage maps. Not affiliated with Cal OES or any utility. Utility outage id SCE 136932667.